Pembroke project honored with “Sword of Honour”
Pembroke project honored with “Sword of Honour”
06-02-2012
In 2011 ZRE Katowice S.A., as a subcontractor and collaborator of Alstom Power Limited, completed the installation of five gas and steam turbines with total capacity of 2125MWe in Pembroke power plant in Wales. The commitment and professionalism of Alstom - the main contractor of the Project Pembroke and other companies participating in its implementation has been recognized by the highest British safety organization the British Safety Council.
-
Prefabrication of steam piping Piping prefabrication
Prefabrication of steam piping
29-12-2011
In December ZRE Katowice S.A. has completed steam piping prefabrication for the Danish company DP Clean Tech for the Pannon project in Hungary. The scope of work included induction bending of steam pipelines with diameters of 219x16 to 273x22 with prefabrication of ready for assembly components.
-
ZRE Katowice S.A. will build a biomass-fired boiler in Scotland
ZRE Katowice S.A. will build a biomass-fired boiler in Scotland
27-12-2011
In October a contract for the construction of biomass-fired boiler in the Scottish Routhes was signed. The scope of works will include installation of the pressure part, along with the boiler piping. The project will run from February 2012 until August 2012. The contractor is the Danish company AET, for whom the Western Division already completed a similar project in 2011 in Italy.
-
First pipe bends in Jaworzno
18-07-2011
In the past few days the last stage of the induction bending machine was performed. The bending tests were carried out under the supervision of our specialist, machine manufacturer employees as well as TUV and polish certified body inspectors. This ensures the highest quality of service from the very beginning of our piping prefabrication facility operation.
-
We are building a exhaust fumes generator in Wroclaw
In late February and early March starts erection of a exhaust fumes generator. This task is carried out on behalf of ERBUD SA.
-
The assembly of 49 MW boiler in Zignano begun.
The assembly of 49 MW boiler in Zignano begun.
18-10-2010
The erection of the 49 MW biomass fired boiler started in mid September. The works will include the boiler itself, internal pipelines and other boiler pressure parts. Pressure tests are scheduled for 12.02.2011. On 01.10.2010 an additional agreement was signed for the installation of the air and exhaust gas boilers and auxiliary equipment for the same boiler.