CNIM – Ridham Project

Location: Ridham

The Western Division (Zakład Zachód) is executing a contract with a French company CNIM for delivery and installation of 120 tons of external pipelines for a boiler that is fired with municipal wastes in the town of Ridham. The boiler parameters are 460oC, 75 bars and 20t/h.

Currently leak tests for individual modules are in progress. Till now it is the largest contract of the Western Division for pre-manufacturing of external pipelines.

In March 2014 another contract with CNIM was competed for pre-manufacturing and delivery of flue gas and air ducts for the Battlefield project in UK. It was the first subcontract of CNIM to ZRE Katowice. The total amount of steel ducts delivered to the construction site was 32,064 kg