Project in Kozienice – Mitsubishi Hitachi Power System (MHPS)

Location: Kozienice

Deadline: 02.2015 - 10.2016

On 29th January 2014  ZRE Katowice  and MHPS signed a letter of intention and contractual terms  and on 19th September 2014 a formal order was assigned to carry out installation of a turbine unit with the power of 1075 MW at the Electric Power Plant in Kozienice that is the largest turbine unit that has been erected in Poland so far.

The project comprises operations associated with installation of a steam turbine and heavy erection of a steam condenser. The scope also includes installation of the Automatic & Control systems.

The scope of the jobs to be carried out by ZRE within heavy erection of the steam condenser includes development of the detailed engineering documentation for the existing concept of installation and erection and supplies of necessary steel structures together with instrumentation.

The field works are scheduled to be commenced in February 2015 and the deadline for completion of erection is planned for October 2016.