Babcock Wilcox & Volund – Peterborough Project

Location: Peterborough

Deadline: 04.2015

On 21st August “heavy erection” of a boiler fired with municipal wastes was completed in Peterborough, UK. The project was carried out for the Danish company called BWV. It is a subsequent subcontract that is carried out by ZRE for that Danish client, but the first one that includes also erection of a boiler.

The boiler parameters are the following: performance of 35.6t/h, steam pressure of 95 bars, steam temperature 455oC.

Pressure test of the boiler is scheduled to February 2015.

For the same project ZRE Katowice is responsible, upon a separate assignment, for engineering, pre‑production and assembling of external pipelines. The amount of the assignment is estimated to ca. 70 tons of pipelines with suspensions and supports.