1. Design work
2. Execution of bended arches
3. Prefabrication of pipelines
4. Installation of the pressure part of the pipeline (mats Xl0CrMoVNb9-1, 323,9x22,2 and 406,4x28)
5. Delivery and assembly of support structures for fresh steam pipelines
6. Installation and adjustment of fresh steam suspensions
7. Performing diagnostic tests [RT, UT, MT, VT] and functional tests
8. Modernization of suspensions according to project guidelines
9. Delivery and assembly of the indicated suspensions
10. Geodetic measurements of pipelines and load-bearing structures
11. Implementation of settings and adjustment of spring suspension
12. Installation and disassembly of installations for blowing pipelines
13. Installation support during blowing